Project Done

BHCC Construction Pte Ltd

Repair Cracks on R.C slab at viewing Gallery Hanger 1 Building using Unifor Crack Injection System(Epoxy Grouting) for Seletar Airport.

Jan 13

Cyclect Electrical & Engineering Pte Ltd

To core holes on R.C. wall for SLNG (Jurong Island) Project.

Feb 13- Aug 13

SK E&C Singapore Branch

Repair dry cracks on R.C. wall in Cut and Cover using Unifor Crack Injection System; repair water leakage/seepage on wall and RC Segment in Bored Tunnel and Tunnel Eye using Unifor Polyurethane Grouting Method and Unifor Underwater Epoxy Grouting Method for MRT DTL 2 C913/C915 Projects.

Mar 13 – Sept 15

Prima Limited

Repair spalling concrete on R.C. soffit using Patching Method for Prima Building.

Mar 13 – Dec 13

Ryobi Kiso (S) Pte Ltd

Grout void on bored pile using Unifor Polyurethane Grouting Method for MRT DTL C912 Project.

May 13 – Apr 13

Kimly Construction Pte Ltd

Repair water leakage from cracks/construction joints/honeycomb on R.C. wall/slab using Unifor Polyurethane Grouting Method for Sophia Residence Project.

Jun 13 – Sep 13

Hexacon Construction Pte Ltd

Repair dry cracks on R.C. wall using Unifor Crack Injection System (Epoxy Grouting) for Skyline Residence Project.

Jul 13

Samsung C&T Corporation

Repair water leakage from cracks/honeycomb and construction joint using Unifor Polyurethane Grouting Method for Suntec City A&A Works.

Jul 13

KTC Civil Engineering & Construction Pte Ltd

Grout void on bored pile using Unifor Underwater Epoxy Grouting Method (UF Grout UW) for MRT DTL3 C925A Project.

Jun 13 – Feb 14

Asset Protection Services Pte Ltd

Repair cracks on R.C. Slab using Unifor Crack Injection System for SAEL Project.

Jul – Sep 13

Leighton Offshore - John Holland J.V

Repair water leakage and dry crack inside cut and cover station using Unifor Polyurethane Grouting Method and Unifor Crack Injection System (Epoxy Grouting) for MRT DT2L C935 Project.

Sep - Dec 13

Bestem Construction Pte Ltd

Repair water leakage on cracks/ construction joints on R.C. Soffit using Unifor Polyurethane Grouting Method for Capitol Building Project.

Jan – Jun 14

SK E & C Singapore Branch

Repair water leakage from cracks/ construction joints and honeycomb on R.C. wall/soffit at cross passage inside tunnel using Unifor Polyurethane Grouting Method (Hycel UF-08) for MRT DTL Stage 2-C918A Project.

Nov 13 – Jan 15

Taikisha Singapore Pte Ltd

Repair water leakage and honeycomb on construction joints and tie rod on R.C. water tank wall using Unifor Underwater Epoxy Grouting Method (UF Grout UW) and Cementitious Pressure Grouting Method (Conbextra GP) for 48 Changi Business Park Project.

Nov 13 – Feb 15